We were out this long weekend digging. We had to get the top of the crawlspace lowered by about 6 inches to meet code (distance to wood). We're going to encapsulate the crawlspace but the building code doesn't account for that apparently. They also made good progress on the retaining wall for the driveway. Even with the large amount of rain I think we'll be able to finish this part of the project in the next week.
Driveway retaining wall being formed
A view from the road looking at the driveway
What we dug out. The requirement was 18" from the lower wall.