Monday, January 6, 2014

The slab & gradebeam pour begins!

After a bit of a delay the pour of the lower foundation begins!









Finishing up!

4 comments:

  1. How many yards was the 1st pour?

    ReplyDelete
  2. Technically its the 2nd pour. 1st pour was the caissons which was about 45yds. This lower section will end up around 40yds. Another 2 pours to go which should be significantly smaller

    ReplyDelete
  3. OMG, 85 yds with 2 pours to go. You'll have $25k just in concrete by the time all pours are complete. That's A LOT of concrete!!! Wow,

    ReplyDelete
  4. I got an edited total today it came out to 47 yards.. so even a little bit more..
    At least its 30% fly ash concrete. So we're helping to clean up the environment some!