Waterproofing 1/29

Waterproofing going in along the perimeter foundation and along the retaining walls.





Sunday, January 26, 2014

Construction Timelapse 1/18 through 1/26

Pics from this weekend 1/25 - Drainage work!

This weekend was about the perimeter drain around the foundation. We laid class b permeable drain rock (8 yards worth) as well as all the perimeter french drain & solid pipe. This type of rock has recycled concrete aggregate.

Foundation walls with forms off

Base layer going in

Tools of the trade

Buried french drain on the top

French & solid drain going downhill

view from top corner

another view from the corner



Filling behind main retaining wall

Sunday, January 19, 2014

Pictures from this weekend 1/18

Pics from this weekend. The foundation pour is complete. Forms are off the lower section.

Garage foundation wall
view of lower foundation with forms off
newly poured upper foundation , entrance
Upper where the main floor meets the hill
view from upper corner

Timelapse 1/12 to 1/18

Sunday, January 12, 2014

Pictures from this weekend 1/12

Garage area with dirt in the middle



Upper gradebeam forms



The first floor finished in the house - The mudroom!

View from lower corner of home

Timelapse 1/4 to 1/12

Monday, January 6, 2014

The slab & gradebeam pour begins!

After a bit of a delay the pour of the lower foundation begins!









Finishing up!

Pre-Pour pictures 1/4

Some pictures right before the scheduled lower level pour tomorrow:

forms braced, tiedowns in and ready to go

that will be an 11" thick slab