Wednesday, April 30, 2014
Windows In!
Last couple days have been all about getting windows flashed and put in..
Next up is finishing up the exterior finishes: roof, siding, stucco, rock..
Next up is finishing up the exterior finishes: roof, siding, stucco, rock..
Sunday, April 27, 2014
Weekend Progress!
This Saturday we finished the roof of the house. Had a 2man crew finish up the sheathing. Too bad it was just 1 day after a lot of rain .. so the interior was soaked unfortunately. Spent a bit of time getting water out of the lower floor mudroom.
Sunday I only had a few hours to work but we put it to good use with a little family help.. Started with the exterior air sealing and housewrap. Using 3M 8067 All Weather Flashing Tape, & Tyvek Commercial-D housewrap. Got to use a Stinger brand cap nailer for the wrap too.
This was only about half way around the main floor story. But the rest requires extensive use of very tall ladders! Windows openings are ready for my expensive flexwrap tape. Then windows go in then flashing tape. We're almost dried in!
| Finishing up the last of the sheathing on the roof |
![]() |
| How its looking from the road |
| Air sealing seams ahead of the Tyvek with this crazy 3M tape (stickiest tape I've ever used) |
| Tyvek Commercial-D drain wrap (the crinkled stuff) |
| Made it around 1 corner |
| then a few others.. |
Tuesday, April 22, 2014
Monday, April 21, 2014
Saturday, April 19, 2014
Trusses being put up
Trusses being delivered!
This was a big day. Our roof trusses were delivered. We had thought there was no way we could get the boom truck to drop the trusses on top of the roof deck. But with some interesting positioning and crane operator skill they were very successfull at unloading all the roof trusses up even through all the trees. Here are pics of the day:



| notice truck has one support on 'shed' pad |
Short vid of lift:
Subscribe to:
Posts (Atom)