Milovic Residence
Monday, November 25, 2013
Pumping day!
After a bit of a rain delay from last week, we have finally starting pumping concrete!
A pretty big milestone as this represents the first 'structure' at the site.
Concrete being delivered into pump
Concrete being pumped up to the uphill caissons.
Wednesday, November 20, 2013
Timelapse Construction 3 - Rebar!
Rebar and more rebar..
This past week was all about rebar...
Rebar for the caisson being assembled
Pile of assembled rebar
Monday, November 11, 2013
Timelapse video take 2
Native resident..
One frame of my timelapse camera showed this curious onlooker. Looks like a young buck.
Young buck inspecting the site...
Drilling progress..
Drilling was mostly complete by this past weekend..
Holes dug. 18 feet is awfully deep in person.
Thursday, November 7, 2013
Drilling has started!
Drilling for the piers started today. Should take a couple days to get them all in. Next up is rebar, inspection, then pouring.
Top right most pier location
Drill rig on the top most level
Newer Posts